Work Report for Construction
Date:
October 17, 2024
Prepared By:
John Smith, Site Supervisor
Project:
Oakwood Apartments – Phase 2
1. Introduction
This report outlines the progress, completed tasks, and challenges faced during the week of October 10-16, 2024, for the Oakwood Apartments construction project.
2. Summary of Tasks and Activities
- Foundation Work:
- Completed concrete pouring for Block A.
- Conducted structural inspections.
- Framing:
- Installed steel frames for floors 2 and 3 of Block B.
- Utility Installation:
- Laid out plumbing and electrical lines for Block A.
3. Results and Achievements
- On-Schedule Progress: Foundation work completed as planned.
- Quality Checks: Passed all structural inspections with no issues.
4. Challenges and Solutions
- Challenge: Delayed delivery of steel beams.
- Solution: Rescheduled framing tasks and coordinated with suppliers for expedited delivery.
5. Upcoming Tasks
- Roofing: Begin installation on Block A.
- Window Installation: Scheduled for Block B, floors 1-3.