Work Report for Construction

Last Updated: October 17, 2024

Work Report for Construction

Date:
October 17, 2024

Prepared By:
John Smith, Site Supervisor

Project:
Oakwood Apartments – Phase 2

1. Introduction

This report outlines the progress, completed tasks, and challenges faced during the week of October 10-16, 2024, for the Oakwood Apartments construction project.

2. Summary of Tasks and Activities

  • Foundation Work:
    • Completed concrete pouring for Block A.
    • Conducted structural inspections.
  • Framing:
    • Installed steel frames for floors 2 and 3 of Block B.
  • Utility Installation:
    • Laid out plumbing and electrical lines for Block A.

3. Results and Achievements

  • On-Schedule Progress: Foundation work completed as planned.
  • Quality Checks: Passed all structural inspections with no issues.

4. Challenges and Solutions

  • Challenge: Delayed delivery of steel beams.
    • Solution: Rescheduled framing tasks and coordinated with suppliers for expedited delivery.

5. Upcoming Tasks

  • Roofing: Begin installation on Block A.
  • Window Installation: Scheduled for Block B, floors 1-3.